Core Scientific Exits Bitcoin Mining as AI Colocation Surges

Core Scientific announced it will complete its exit from Bitcoin mining by the end of 2026, transitioning to a pure-play high-density colocation provider for artificial intelligence and high-performance computing workloads. The shift marks a dramatic reversal for a former mining heavyweight, with mining now contributing only 7.5% of quarterly revenue while colocation services generate over 90%.

Key takeaways

  • Core Scientific targets year-end 2026 to finish winding down all Bitcoin mining operations.
  • Colocation revenue surged nearly 60% sequentially to $215.4 million in Q3, representing roughly 92% of total revenue.
  • Self-mining revenue collapsed 79% year-over-year to $12.3 million and posted a $7.5 million gross loss.
  • The company has reduced its active miner fleet by nearly 50% since the end of 2025.
  • Adjusted EBITDA more than tripled quarter-over-quarter to $133.6 million with a 57% margin.

Mining revenue collapses as colocation takes over

Third-quarter results filed with the SEC show the extent of the transformation. Total revenue reached $232.9 million, but digital asset self-mining contributed only $12.3 million, down from $57.4 million a year earlier. Hosted mining for third parties added just $5.2 million. Together, mining activities produced $17.5 million, or 7.5% of the quarter’s revenue. In contrast, colocation services delivered $215.4 million. The gross profit picture is equally stark: self-mining recorded a $7.5 million loss, while colocation generated $128.4 million in gross profit at a 60% margin. Adjusted EBITDA jumped to $133.6 million, lifting the margin to 57% from 25% in the prior quarter.

AI hosting deals drive infrastructure repurposing

The pivot began in 2024 with an initial hosting agreement with CoreWeave in March, followed by a larger deal in June. As of September 30, Core Scientific was billing for 485 megawatts of colocation capacity, up 90 MW during the quarter, representing more than $700 million in average annualized GAAP revenue. An additional roughly 100 MW under the CoreWeave buildout is in commissioning and expected to start recognizing revenue in the coming months. Beyond CoreWeave’s contracted 590 MW, the company has 530 MW under an AMD-backed agreement across five campuses, with initial delivery targeted for the first half of 2027. Power and floor space are being repurposed under long-term customer agreements as circumstances allow.

Impairments and contract terminations mark transition costs

The exit has carried significant one-time charges. In the first quarter of 2026, Core Scientific recorded $266.5 million in mining-related asset impairments, citing weaker Bitcoin prices, historically low hashprice, and falling equipment values in the secondary market. During the second quarter, the company terminated its mining equipment agreement with Block and Proto, resulting in a $41.9 million loss as part of the transition. These writedowns reflect the declining economics of the mining fleet as the company redirects capital toward data center infrastructure.

Regulatory uncertainty clouds data center expansion

The planned exit coincides with fresh political uncertainty for large-scale data center development in the United States. Following the midterm elections, opponents of data-center expansion were among the winners of Democratic gains, according to Reuters. The backlash centers partly on rising electricity bills for residential customers and the heavy demands these facilities place on local power and water resources. This regulatory environment could affect the pace and cost of future campus buildouts for Core Scientific and its peers.

What this means for traders

Market participants should monitor whether colocation revenue continues its sequential growth trajectory and whether the remaining CoreWeave and AMD-backed capacity comes online as scheduled. The trajectory of adjusted EBITDA margins will signal how efficiently the company converts new leases into earnings. Additionally, watch for regulatory developments at state and local levels that could increase compliance costs or delay permitting for high-density facilities. The broader trend of public miners pivoting to AI hosting may accelerate if the funding gap between well-capitalized operators and smaller peers continues to widen.

Frequently asked questions

When will Core Scientific stop Bitcoin mining?

Core Scientific expects to complete its exit from Bitcoin mining by the end of 2026, with the wind-down finishing during the fourth quarter according to both the CFO and CEO.

How much revenue does colocation generate for Core Scientific?

Colocation revenue reached $215.4 million in the third quarter, accounting for roughly 92% of total revenue, with more than $700 million in average annualized GAAP revenue from 485 MW of billed capacity.

What AI hosting agreements does Core Scientific have in place?

Core Scientific has a 590 MW agreement with CoreWeave and a 530 MW AMD-backed agreement across five campuses, with initial delivery on the latter targeted for the first half of 2027.

Get live signals and free trading courses in the ForexMentor app for Windows. Download the app

Crypto assets are highly volatile, and new tokens that have not been officially recognised are not reliable until they are. This article reports the news and is not financial advice. The decision is yours.

Leave a comment

Your email address will not be published. Required fields are marked *